Earned Value Management Calculator

Earned value management: cost and schedule performance, forecast final cost.

100% FreeNo sign-upPrivate — runs in your browser
—

cost performance index (CPI)

Cost variance CV (EV-AC)
—
Schedule variance SV (EV-PV)
—
Cost performance index CPI
—
Schedule performance index SPI
—
Estimate at completion EAC
—
Estimate to complete ETC
—
Variance at completion VAC
—
% complete (EV/BAC)
—

Copied!

How to use this tool

1
Enter planned and earned value

PV is what should be done; EV is what is actually done, in budget terms.

2
Enter actual cost

AC is what the completed work really cost.

3
Enter the total budget

BAC is the approved budget for all work.

4
Read indices and forecast

CPI/SPI show health now; EAC and VAC forecast the finish.

Formula & worked example

PV = planned value, EV = earned value, AC = actual cost, BAC = budget at completion. CV = EV – AC, SV = EV – PV, CPI = EV / AC, SPI = EV / PV, EAC = AC + (BAC – EV) / CPI, ETC = EAC – AC, VAC = BAC – EAC. Indices below 1.0 mean over budget (CPI) or behind schedule (SPI).

Worked example: PV $100,000, EV $90,000, AC $100,000, BAC $200,000. CV = -$10,000, SV = -$10,000, CPI = 0.90, SPI = 0.90. EAC = $100,000 + ($200,000 – $90,000) / 0.90 = $222,222. ETC = $122,222. VAC = $200,000 – $222,222 = -$22,222.

Limitations — read this before you rely on it

EVM quality depends entirely on honest percent-complete and a sound baseline: inflated EV flatters both indices. The EAC formula used here assumes current cost performance continues; other EAC formulas suit different causes of variance.

Frequently asked questions

The budgeted value of work actually completed. Comparing it with planned value and actual cost separates schedule problems from cost problems.

CPI = EV/AC: above 1 is under budget. SPI = EV/PV: above 1 is ahead of schedule. Below 1 is over budget or behind schedule.

No. This is a calculator from the numbers you enter. Tax, legal and investment decisions depend on your full circumstances, so check with a qualified professional for real decisions.

As accurate as the inputs and the stated formula. It is a model with simplifications listed in the limitations; try a range of inputs rather than trusting one figure.

Yes for the maths, which is currency-neutral unless a jurisdiction is stated. Tax rules, thresholds and market conventions differ by country, so check local rules where they matter.